In 2019 started the complete redesign of the interior of the lategothic church Oberneukirchen (Upper Austria) from the 15th century. The general renovation included, among other things, the renewal of the floor, renovation of the organ, rear ventilation of the windows, installation of a new bench heating system based on infrared, renewal of the electrical installations, lighting and loudspeaker system, restoration of the church pews up to the redesign of the sanctuary.
HAINZL installed the entire electrical engineering in the building complex with modern and new technology. Specifically, this included the complete low voltage distribution, the high and low voltage installations, the LAN cabling (network technology), the entire lighting cabling and, as a highlight, a multifunctional control panel (see picture) for optimum control of the lighting system, the heating, the sound system, as well as the bell and window control.
Execution period: 06.2019 - 03.2020
Further projects of the business unit building services engineering can be found here.